Atlantic Avenue Is Done. The Lyons Road Stretch Past Canyon Isles Is Still Waiting.

November 12, 2026

Head south from Canyon Isles on Lyons Road and you are on two lanes. Turn onto Atlantic Avenue and you reach an intersection with three through lanes in each direction, dual left-turn lanes, a right-turn lane each way, and buffered bike lanes running west toward State Road 7. That intersection is new. The road leading to it from Canyon Isles is not.

The improvement Canyon Isles drivers can use this month is at the far end of their route. The stretch of Lyons Road in front of the community is where the next round of construction will happen, and as of the county's latest listing, which shows rebid bids received November 3, the contract award is still pending.

What Opened at the South End

The Florida Department of Transportation's State Road 806/Atlantic Avenue Reconstruction Project started on January 20, 2025. Its 2.760-mile project limits ran along Atlantic Avenue from west of State Road 7/US 441 to just east of Florida's Turnpike and included a section of State Road 7 itself. The project page still lists Spring 2028 as its completion date. Next to that date, it now says the project was completed 20 months early. FDOT's Palm Beach County traffic report for October 23 to 30, 2026 says the department gave the $26 million project final acceptance on Friday, October 16, 2026.

Here is what a Canyon Isles driver now has at that end of the route:

  • Atlantic Avenue widened from two lanes to four between west of State Road 7 and east of Lyons Road, and from four lanes to six between Lyons Road and the Turnpike.
  • At Lyons Road and Atlantic Avenue, three eastbound and three westbound through lanes, dual left-turn lanes, and single right-turn lanes.
  • Continuous 6-foot sidewalks and 7-foot buffered bike lanes in both directions from State Road 7 to east of Lyons, plus an 8-foot sidewalk on the westbound side from east of Lyons to west of the Turnpike.
  • A third through lane each way at Atlantic and State Road 7, and fiber optic cable connecting the signals along the corridor.

The contractor was OHLA-USA, Inc. If your routine takes you south to Delray Marketplace at 14851 Lyons Road, or west toward State Road 7, the finished part of the corridor is the part you reach last.

Two Projects, Two Very Different Clocks

The stretch of Lyons Road that the county plans to widen first runs from the Lake Worth Drainage District L-30 canal north to Boynton Beach Boulevard. On Palm Beach County's Agricultural Reserve road improvements map, Canyon Isles and Canyon Lakes sit along that segment.

Atlantic Avenue reconstruction Lyons Road Phase 1
Agency FDOT District 4 Palm Beach County Engineering
Limits West of SR 7 to east of the Turnpike L-30 canal to Boynton Beach Blvd
Lane change 2 to 4 lanes, and 4 to 6 east of Lyons 2 to 4 lanes
Status in November 2026 Final acceptance October 16, 2026 Rebid bids received November 3, 2026; award pending
Contractor OHLA-USA, Inc. Not yet awarded
Cost $26 million About $16.5 million engineer's estimate, per The Boynton Weekly

The Lyons project combines two county project numbers, 2018503 and 2020110. The second covers improvements at the Lyons Road and Boynton Beach Boulevard intersection. For Canyon Isles, that means the work will cover both the road outside the community and the intersection at its north end.

How the Lyons Schedule Has Moved

The county's road improvements sheet, revised May 29, 2026, laid out a schedule. Bid documents and newer county listings show how it has gone since then:

  1. December 2025. Final roadway plans complete, with permits and Palm Beach County Water Utilities relocation plans still being finished.
  2. June/July 2026. The county planned to advertise for bids, a step it had pushed back from spring so staff could finish agreements with FDOT and Water Utilities.
  3. July 24 to August 25, 2026. The first solicitation was posted, with bids due August 25. The county's bid documents page now marks that round "BID CANCELLED."
  4. October 29, 2026. The rebid was posted.
  5. November 3, 2026. Rebid bids were received. Award and resolution are both listed as pending.
  6. January 2027 and January 2029. These were the May forecasts for the contractor's notice to proceed and for construction completion.

The May sheet expected county commissioners to award the contract in October or November 2026. The Board of County Commissioners agenda for November 10 listed one Engineering and Public Works item, a change order for Gateway Boulevard and High Ridge Road, and no Lyons Road item. January 2027 and January 2029 are best treated as the county's last published targets. The project's real clock starts on the day the commission awards the contract.

What the Work Will Look Like From Your Car

The bid documents describe a project that goes well beyond adding lanes. The first solicitation covered about 3.189 miles of milling, resurfacing, and new pavement, along with drainage, curb and gutter, lighting, signing and markings, signals, and utility coordination. The county sheet says the utility relocations will be done as part of construction.

The rebid summary on GovTribe lists more detail.

  • Trees. Removal and retention across more than 700 trees, with protective barricades required around the trees being kept.
  • Light. 55 lighting poles along the main Lyons segment.
  • Signals. Three mast arm assemblies and seven vehicular signals on Lyons, plus two mast arm assemblies and nine signal heads at the Boynton Beach Boulevard intersection.
  • Timing. New signals go through a 90-day burn-in period after conditional acceptance.
  • Lane closures. Traffic control plans must be submitted at least two weeks ahead, and no lane closures are allowed during the morning and evening peak hours.

The tree count and the lighting poles will change how the road looks. The peak-hour rule shapes when you are likely to see work crews. Under the bid terms, lane closures belong to the middle of the day and off-peak hours, not to the school-run and commute windows.

Work on Lyons has already started in a smaller way. The county's road and bridge construction list for November 2 through 8 showed periodic lane closures on Lyons Road from Boynton Beach Boulevard north to Hypoluxo Road to refurbish the existing thermoplastic markings. That is a sales tax project and separate from the widening.

Why Four Lanes Has Been a Corridor Issue for a While

The widening has been a public topic along Lyons for more than a year. WFLX reported that at a June 18, 2025 county zoning hearing on 37 additional homes in a Lyons Road community, Commissioner Maria Sachs asked that those units wait until the road was widened.

"What I'm saying is, not now. Wait until Lyons Road is extended to four."

In the same WFLX story, Barbara Roth, president of the Coalition of Boynton West Residential Associations, described the request as a matter of timing. "We are just asking for time to catch up," she said. In August 2026, The Boynton Weekly described Lyons as one of the busiest north-south routes in western Boynton and noted that construction could bring temporary delays.

The Two Lanes Between Canyon Isles and Atlantic

Phase 1 stops at the L-30 canal. The section from there south to Atlantic Avenue is Phase 2, also planned as a widening from two lanes to four. The county sheet says Phase 2 could be awarded in 2029 so that work can begin as soon as Phase 1 is finished. Its plans are on hold while the county waits for FDOT to confirm right-of-way and environmental impacts, because of how much FDOT funding is available.

For the next several years, then, the drive south from Canyon Isles runs on two lanes into an intersection built for six through lanes on Atlantic. The third piece of the county's plan is a new section of Flavor Pict Road running from Lyons Road over the Turnpike to Hagen Ranch Road. It is still in design: the 65% plans are under review, and permit applications to the Lake Worth Drainage District, the Army Corps of Engineers, the South Florida Water Management District, and FDOT/Turnpike are pending.

The Lyons rebid appears on the county's Roadway Production bid documents page under projects 2018503 and 2020110, where the award and resolution are listed as pending. When that entry shows a resolution number, the construction timeline for the road outside Canyon Isles will finally have a fixed start.